Footing Pad Installation
 
The posts (min. 4x4) location or spacing is to be determined by the deck area to be supported by the post for the local soil capacity (See Support Information).
  • Dig the hole a little larger than 10” in diameter and deep enough to be below the local frost line. Clean out loose soil and level bottom of hole.
  • Place the Footing Pad into the hole smooth side down.
  • Use the post to tamp the Footing Pad into place.
  • Position the post on the pad to the specific location
  • Replace the dirt around the footing and compact.